Projects / P-101
Redbrick Property Group: Rewire and fire alarm upgrade
Redbrick Property Group · Brook House (Block A), M15 5RR · 30 Sept to 27 Dec
On site
Monthly valuations on the 25th. Retention 5%, half back at practical completion.
55%Valued £36,048 of £65,840
£9,850Invoiced so far
£26,198Done, not invoiced yet (WIP)
£4,171 · 88%Cost so far against £49,126 budget
Jobs on this project
#4807 · Annual boiler serviceContainment and cabling · sent to K. Walsh Contracting · 17 Nov
Job done#4814 · Annual landlord gas safetySecond fix and fire alarm · 17 Nov
Job done#4877 · Quarterly plant room checkStrip out and first fix · 17 Nov
BookedExtra work: variations and dayworks
V-003 · Daywork: Lifted and relaid floorboards in two rooms the main contractor had screwed down. Not in the spec.6h labour, 1 × Screws (box) · raised by K. Walsh Contracting
£419Sent to the customerV-002 · Variation: Customer asked for 6 extra double sockets in the meeting room.4h labour, 6 × 1-gang light switch · raised by Ellie Burke · agreed by Redbrick Property Group
£1,840Customer said yesLog a variation or daywork
Applications for payment
Application 1 · to 12 OctValued £10,368, less retention £518, less before £0
£9,850PaidApplication 2 · to 11 NovValued £24,240 (with £1,840 extras), less retention £1,212, less before £9,850
£13,178Sent to the customerRetention
Held by the customer: £1,212. 50% comes back at practical completion, the rest 12 months after.
Working under a main contractor
Not set up as a subcontract: no CIS taken off and VAT charged as normal.CIS only comes off the labour, never the materials. Reverse charge is for construction work for another VAT registered contractor, not the end customer.
Costs against the project
K. Walsh Contracting · KW-0412Labour £1,320, materials £85, CIS 20% £264 held back
£1,405Northern Containment Ltd · NCL-2290Labour £2,100, materials £640
£2,740