Stock and buyingProjects
New job
Projects / P-101

Redbrick Property Group: Rewire and fire alarm upgrade

Redbrick Property Group · Brook House (Block A), M15 5RR · 30 Sept to 27 Dec

On site
Monthly valuations on the 25th. Retention 5%, half back at practical completion.
55%Valued £36,048 of £65,840
£9,850Invoiced so far
£26,198Done, not invoiced yet (WIP)
£4,171 · 88%Cost so far against £49,126 budget

Stages

Contract sum
StageValue £Budget £Cost so far% doneValued
Strip out and first fix1 job£0£8,294 left£11,520
Containment and cabling1 job£1,405£17,309 left£17,408
Second fix and fire alarm1 job£26£15,180 left£5,280
Test, certify and hand over0 jobs£0£6,912 left£0

Jobs on this project

#4807 · Annual boiler serviceContainment and cabling · sent to K. Walsh Contracting · 17 Nov
Job done
#4814 · Annual landlord gas safetySecond fix and fire alarm · 17 Nov
Job done
#4877 · Quarterly plant room checkStrip out and first fix · 17 Nov
Booked

Extra work: variations and dayworks

V-003 · Daywork: Lifted and relaid floorboards in two rooms the main contractor had screwed down. Not in the spec.6h labour, 1 × Screws (box) · raised by K. Walsh Contracting
£419Sent to the customer
V-002 · Variation: Customer asked for 6 extra double sockets in the meeting room.4h labour, 6 × 1-gang light switch · raised by Ellie Burke · agreed by Redbrick Property Group
£1,840Customer said yes
Log a variation or daywork

Applications for payment

Application 1 · to 12 OctValued £10,368, less retention £518, less before £0
£9,850Paid
Application 2 · to 11 NovValued £24,240 (with £1,840 extras), less retention £1,212, less before £9,850
£13,178Sent to the customer
Next: application 3Valued £36,048, less retention £1,802 (5%), less before £23,028 = £11,218 due

Retention

Held by the customer: £1,212. 50% comes back at practical completion, the rest 12 months after.

Working under a main contractor

Not set up as a subcontract: no CIS taken off and VAT charged as normal.
CIS only comes off the labour, never the materials. Reverse charge is for construction work for another VAT registered contractor, not the end customer.

Costs against the project

K. Walsh Contracting · KW-0412Labour £1,320, materials £85, CIS 20% £264 held back
£1,405
Northern Containment Ltd · NCL-2290Labour £2,100, materials £640
£2,740